allan666
Well-known member
i have been erecting 4 scaffolds for asbestos removal which need to be sheeted in , no hi abs or fork lifts are allowed on site so we couldnt use kentlage blocks to weigh them down . the designer has decided we need to use tube intead , 125 continuos in the base and 54 continuos on the roof .this comes to over 2000 21 foot tubes and a good few hundred shorter.over a thousand of these are on the back of the job so have to be walked over a hundred foot and includes passing them through a window .a few hundred of these need passed up onto the roof .the ones put in the base need to be passed in from the end cos of the bay sizes . the 2 scaffolds on the front still have quite a walk to them and one of them is between 2 walls so will be an absolute nightmare . how long should a squad of three take to do this . i will post later how many hours i have been given to do this and erect the four scaffolds , cheers lads