Lift Heights (1 Viewer)

It's a pyramid shaped bracing pattern often used to support the end of a cantilivered beam or steel section.

Basically, you punch a tube up at the end support for the cantiliver and brace back to a tie or node point. You then fix a pull-back tube the opposite way onto the section you are supporting.

Dolphin bracing.

yeah thats the fecker thats the techo explanation
 
Just come back from site and this is what I said he will get!!!

Base @ 2.0m
2nd @ 1.4m = 3.4m (floor level)
3rd @ 2.6m
4th @ 2.6m
5th 450mm below eaves for roofing.

2nd lift adapted/raised to 2.0m for render
3rd lift then becomes 2.0m
Roof lift off.

The good thing was he seemed impressed took a copy of my sketch and said everyone else will price the same!!!

So if i dont get it, it's me own freckin fault:laugh:
 