Good morning Guys
Just after a bit of clarifacation into the testing of anchors according to TG4:11
It lists on the guidance note the following
Proof tests.
These are needed to check that anchors to be used in the job have been installed correctly. They should be carried out on all projects. This guidance applies to all new jobs and to structures with previously installed anchors. A sample of anchors .....ect
which i fully understand,then it lists
6.4 Test Procedures
Site tests should be carried out by suitably competent personnel (other than the actual installer of the fixings tested) using a test meter with a gauge calibrated within the last twelve months to an accuracy of < 5%. Test equipment should apply the load to the anchor and not through the tie through suitable couplers and be arranged such that the reaction loads are taken sufficiently far from the anchor so as not to influence the result, typically this means ensuring the feet of the bridge do not rest on the masonry unit being tested.
does this mean a second suitably qualified operative (not involved in the erection of the scaffold )has to do the required pull test and sign off the test,i know this stops conflict of interest of the pull test but also adds extra cost to each project(surely that would mean a operative going around all day doing pull tests),and more interesting does anybody out there actually proceed in this way.
I know these are guidance notes,but in relation to a independent operative doing the pull test do we need to comply with them legally,
your comments are most welcome.
Just after a bit of clarifacation into the testing of anchors according to TG4:11
It lists on the guidance note the following
Proof tests.
These are needed to check that anchors to be used in the job have been installed correctly. They should be carried out on all projects. This guidance applies to all new jobs and to structures with previously installed anchors. A sample of anchors .....ect
which i fully understand,then it lists
6.4 Test Procedures
Site tests should be carried out by suitably competent personnel (other than the actual installer of the fixings tested) using a test meter with a gauge calibrated within the last twelve months to an accuracy of < 5%. Test equipment should apply the load to the anchor and not through the tie through suitable couplers and be arranged such that the reaction loads are taken sufficiently far from the anchor so as not to influence the result, typically this means ensuring the feet of the bridge do not rest on the masonry unit being tested.
does this mean a second suitably qualified operative (not involved in the erection of the scaffold )has to do the required pull test and sign off the test,i know this stops conflict of interest of the pull test but also adds extra cost to each project(surely that would mean a operative going around all day doing pull tests),and more interesting does anybody out there actually proceed in this way.
I know these are guidance notes,but in relation to a independent operative doing the pull test do we need to comply with them legally,
your comments are most welcome.