how long would you expect to take on this man hours gang of three

gable end 2 boards wide 3 lift(between two buildings tite) top lift opended up to 3 boards top lif boarded 16 bays @ 10ft

back 14 bays @ 8ft returned with beams and 1 boarded lift on beams 20f
3 lifts top lift boarded

front 14 bays at 8ft with 3 board canterleaver brack top lift to a 8ft bay top lift boarded again

other gable 6 towers 8 ft 2 lift inside topped out handrails round flat roof all easy acces oher than 1 gable how long would you give 3 to do it ?
 
Layher is maybe the best System in the market today.
Ive used most of the big names: Haki, CupLok, KwikStage, Peri, GAS, Van Thiel and Layher smashes them all, with ease.

Its also fast. Very very fast to use.
 
Layher And Plus Eight Are Probably The Two Fastest And Best Systems On The Market Today, And Iv Used Most Of Them.
 
If i read it right scaff i would expect them to do it in 5 days in tube and fittings without any problems at all
 
I hate these questions but would guess 3 days. The usual, lot of factors blah blah blah.
 