If everything goes to plan i should have 4,big new builds to start when and if i get my loan,
Ive mock qouted one,proggressive 3 lifts for mason and roofer only,no adaptions,
2 sides will need adapting for plastering, the front adapted for a balcony and a horrible chimney,
Should i do these adaptions based on an hourly rate and put it on a Variation order sheet when said jobs are done or try to work out how long said jobs will take plus metreage etc and add on to qoute?
Cheers for any help
John.